Northern Tree Service has been on site this week removing trees on the east side of the street by the Button Building.
Verizon has finished their work by the Pizza House and will be returning next week for some additional line work.
Eversource will be moving to the sidewalk in front of the former Manchester Hardware next week for additional gas relocation work.
Please note that the tree work is essential site preparation and is the early stages of the overall project.
For information and details regarding the approved MassDOT project schedule, please visit https://easthamptonma.gov/661/Union-Street-Project on the City website.
Details of project work are subject to change.